Case ref: MLA/2019/00537
Licence ref: L/2020/00060/1

Case summary

Main content

Project description

Howley Weir
The proposal comprises a single Archimedes screw turbine, a turbine house building, trash screening, access improvements, an electrical substation and underground cabling.
The scheme is expected to generate a peak power output of 160 kW and an average annual energy production of 0.5 GWh.
This is sufficient to power 130 homes and provides an effective CO2e saving of around 260 tonnes per year.
The scheme in its current size and layout is optimal given the project constraints, including hydrology, environmental impact, land ownership and commercial viability.
Please see attached Method Statement

Other information

Applicant details

Ewan Campbell-Lendrum / +44 (0) 7444311018 / ewan@h2opower.limited
H2O POWER LTD / Wellington House 273- 275 High Street, London Colney, St Albans, Hertfordshire / AL2 1HA
17-DEC-2019
23-DEC-2019
16-MAR-2020
Completed
(Discharging conditions)