Project description
Project title
Howley Weir
Project background
The proposal comprises a single Archimedes screw turbine, a turbine house building, trash screening, access improvements, an electrical substation and underground cabling.
The scheme is expected to generate a peak power output of 160 kW and an average annual energy production of 0.5 GWh.
This is sufficient to power 130 homes and provides an effective CO2e saving of around 260 tonnes per year.
The scheme in its current size and layout is optimal given the project constraints, including hydrology, environmental impact, land ownership and commercial viability.
Programme of works
Please see attached Method Statement
Other information
Applicant details
Ewan Campbell-Lendrum / +44 (0) 7444311018 / ewan@h2opower.limited
H2O POWER LTD / Wellington House 273- 275 High Street, London Colney, St Albans, Hertfordshire / AL2 1HA
Date application submitted
17-DEC-2019
Date application validated
23-DEC-2019
Date initial decision made
16-MAR-2020
Status
Completed
(Discharging conditions)