Project description

Portland Marina Pontoons
see uploaded document
Subject to licence issue and plant availability. A 10 year licence is requested so that the pontoons can be installed in smaller phases (up to 6 in number) to suit the economic climate. The installation of the full set of pontoons is estimated to take 24 weeks, each phase being approximately 4 weeks.

Other information

Applicant details

Richard Reddyhoff / 01305 866190 / richardr@deanreddyhoff.co.uk
DEAN & REDDYHOFF LIMITED / Osprey Quay Hamm Beach Road Portland Dorset / DT5 1DX
12-OCT-2017
11-JAN-2024
19-DEC-2017
19-FEB-2024
Completed