Southsea Promenade/ Seawall emergency repairs
Failure of significant 100m of seawall providing coastal flood and erosion protection to the city of Portsmouth. Aim to stabilise the damage to prevent a breach and coastal flooding of 2500 homes as soon as possible.
Emergency Works due on site 30/12/15. Duration unclear at present time. I would expect 2 months to complete emergency works to stabilise the wall given its exposure and further storm damage over the winter period which will damage the proposed works.

Other information

Applicant details

Dr   Andrew Pearce / +44 (0)7974 078 769 / andrew.pearce@havant.gov.uk
PORTSMOUTH CITY COUNCIL / Civic Offices Portsmouith / PO1 2AL
29-DEC-2015
29-DEC-2015
29-DEC-2015
Completed