Case ref: MLA/2013/00426/2
Licence ref: L/2014/00023/3

Case summary

Main content

Project description

Walney Offshore Wind Farm Operational Marine Licence - Inter Array Cable Repair
An operational Marine Licence is sought for emergency inter array cable repairs over the operational life time of the Walney Offshore Wind Farm (1 & 2). The objective of obtaining an operational Marine Licence for emergency inter array cable repairs seeks to ensure adequate contingency plans are in place to react to a major breakage/fault in an inter array cable by reducing the time required to undertake cable repairs when a fault is detected.

Other information

Applicant details

Mr   Hugh Yendole / 02078115200 / HUYEN@Orsted.co.uk
WALNEY (UK) OFFSHORE WINDFARMS LIMITED / 5 Howick Place, Westminster London United Kingdom London / SW1P 1WG
01-NOV-2013
21-NOV-2017
12-FEB-2014
31-JAN-2018
Completed
(Discharging conditions)